Knockmore to Antrim Essential Track Safety Works

Client: Translink
Design and construction to ensure that the railway line between Knockmore and Antrim remained available for diversion route working in a safe physical condition, suitable for running trains at 30mph.
Works included:
- Site clearance- vegetation, scrap rail etc
- Demolition of the disused platform
- Culverts repairs
- Bridge repairs
- Ballast- dropping, tamping and lining
- Sleepers- replacement and upgrade
- Re-construction of user-worked crossings
- Signage
- Track rehabilitation where slurry spots (wet beds) had formed