FP McCann’s dual copings specified on Great North Rail project
Status: Completed
Location: Blackpool North and Kirkham and Washam stations
Division: Railway
Main Contractor: Volker Rail and Siemens
Market Sector: Commercial

FP McCann has supplied over 2000 precast concrete dual copings as part of Network Rail’s Great North Rail electrification programme
J Murphy has installed around 2,250 of FP McCann’s standard dual rail coping units measuring 930mm x 1160mm x 100mm, including a buff tactile in an acid-etched finish. The copings were lifted into place using a specialist concrete vacuum lifter and bedded on a high strength grade mortar. Commenting on the installation of the precast dual coping/tactile units, Enda Murphy Construction Manager for J Murphy said, “Network Rail and our client Volker Rail have been astounded by the amount of work completed on site amidst very harsh weather conditions. As a key component of the complete construction package, this dual coping system significantly reduces the platform build time and has played a major part in ensuring the phased programme of works has been delivered on time. We will certainly consider their use on future platform projects.”
The dual coping/tactile units are manufactured at FP McCann’s Littleport factory in full accordance with the requirements of NR/L3/ CIV/030 and are accredited as conforming to the pendulum test slip resistance requirements of BS EN 13036-4.
For further information about FP McCann’s precast concrete Rail solutions, call our Littleport sales team on 01353 861416 or email: sales@fpmccann.co.uk