This project is part of Translink’s “Better Connected” strategy, which aims to promote sustainable travel and improve public transport accessibility across Northern Ireland.
The Moira site is considered one of Translink’s most important Park and Ride locations due to its position on the busy key southern rail corridor.
The project is the main construction works associated with a new 480 space park and ride facility on a greenfield site to the north of Moira Train Station and supplementary works to the entrance of the existing facility.
The project commenced in July 2025 and is due to be completed in Summer 2026, enabling more people to enjoy the convenience of rail travel and supporting better regional connectivity and reliable alternatives to car-only journeys.


Progress to Date
-Ecological protection measures have been implemented, and the Topsoil has been excavated and stored on site for re-use,
-The retention pond and attenuation tank construction, pictured below, has been completed,
-Main line storm drainage adjacent to Station Road has been installed.
-Essential excavation and installation work has been completed on lands adjacent to Station Road.
-The new footway and widened site entrance, as well as streetlighting along Station Road has been completed, with the carriageway now open to two-way traffic flow.
-Accommodation works to neighbouring properties is currently underway,
-Street lighting installation works adjacent to Station road is currently in progress.
Upcoming Works
-Completion of street lighting installation works along Station Road.
-Commencement of kerbing works in field adjacent to Station Road.
-Commencement of permanent fencing and acoustic barrier fencing along the site perimeter.
-Drainage installation works within upper field and commencement of further essential layering work.