FP McCann was appointed by The Department for Infrastructure as the Principal Contractor for the Moylinn Footbridge Replacement Project in 2025.
Product: Moylinn Footbridge Replacement
Client: DfI Transport and Road Asset Management
NEC Project Manager and Supervisor: Amey
Principal Contractor: FP McCann
Design Team: Design ID supported by SDD
Subcontractor: M Hassan & Sons


The pre-tender conceptual design of the replacement footbridge was completed by DfI and Amey with FP McCann developing the Detailed Design in Partnership with Design ID and Structural Design & Detailing.
Construction of foundations commenced in May 2025, utilising FP McCann’s C40/50 Readymix Concrete sourced from Coote’s Quarry Armagh, which was poured to form the abutments.
Subcontractor M Hassan & Sons manufactured, assembled and installed the single span structural steel truss bridge.
They were aided onsite by Quigley Crane Hire who set the footbridge into position. Traffic management was in place to ensure safety of operations.
FP McCann also supplied aggregated, precast Concrete Manhole Chambers and Blacktop to facilitate backfilling operations, drainage and surfacing of the approach paths leading to each abutment.
The replacement Moylinn Footbridge provides shared pedestrian and cycle access over Lake Road connecting Craigavon’s Active Travel Network.
For further information on FP McCann’s Products, contact the sales team at any of our depots:
- Armagh – 028 3755 1126
- Kilrea – 028 2954 0285
- Knockloughrim – 028 7964 2558
- Lisnaskea – 028 6772 1286
- Larne – 028 2826 0824
- Mallusk – 028 9083 0005